EU mulls tax on Big Tech to boost budget Anthropic worker claims to have solved a holy grail of math problems with the help of AI Denmark’s GomSpace Secures €8M Contract for Blue Origin Moon Mission APOD: 2026 November 21 – Voyager’s Neptune Extreme rainfalls flood Sri Lanka’s coastal city as wetlands, drains vanish - news - Mongabay Hidden cancellation buttons and fake urgency—consumers have grown accustomed to deceptive design online Curiosity Spots Drifting Twilight Clouds Can teams of AI agents recreate the chain reaction of human decisions? Live coverage: SpaceX to launch intelligence-gathering satellites for the National Reconnaissance Office Sri Lanka’s digital ID ambitions face a bigger test: Making government data work - Biometric Update
SRI LANKA NEWS

Cleveland Bridge administration extended as Sri Lankan debt remains unpaid - Construction News

Lanka Hit News • Sep 1, 2026 · 2mo ago • 2 min read
Share:

01 Sep 2026 By CN Contributor : Jenny Eagle

The administration of collapsed Darlington steelwork specialist Cleveland Bridge has been extended by another year.

It comes after administrators at FRP Advisory failed to receive a final payment from the Sri Lankan government, despite the money now being agreed.

In a progress report published on 27 August, FRP said the Sri Lankan Ministry had confirmed that the outstanding payment will be made.

However, the money has still not been received.

Cleveland Bridge went into administration in July 2021. The 140-year-old company was known for its work on major structures including the Sydney Harbour Bridge and Wembley Stadium arch.

Before its collapse, it was involved in a Sri Lankan project to supply and install 250 bridges, backed by £49m of support from UK Export Finance.

The latest filing said around £480,000 remained due to Cleveland Bridge from that project. Around £360,000 of this will then have to be paid to the project’s Sri Lankan subcontractors.

In their last report , the administrators were still waiting for the Sri Lankan Ministry to confirm when the final payment would be released.

FRP has now said the ministry has confirmed the payment has been agreed, but further requests for information continue and the administrators and the Sri Lankan subcontractors are still chasing the money.

FRP said it had also sought help from the British High Commission in Sri Lanka and approached Deutsche Bank, a former funder of the project.

The latest report said the project was now outside its defects liability period and that all defects had been resolved. An addendum to the contracts had also been agreed and approved by the parties.

Due to the payment delay, the administration has now been extended for another year, with a new end date of 21 July 2027.

FRP said the extension was needed to give it more time to recover the money from the Sri Lankan government and deal with the company’s remaining tax and banking matters in Sri Lanka and the UK.

There is still no expected payment for Cleveland Bridge’s unsecured creditors.

UK Export Finance, which previously submitted a claim of around £2m, is therefore not expected to recover any money.

HMRC has received £755,000 so far as a preferential creditor, including a further £30,000 paid during the latest reporting period.

A final payment to HMRC will be made once the remaining Sri Lankan project and banking matters have been resolved, the report said.

HMRC also has a separate unsecured claim of £455,526, for which no return is expected.

The lengthy process has also increased the cost of dealing with the failed company.

FRP said £1.2m in administrator fees, excluding VAT, had been drawn from available funds.

The administrators said they had spent more time than expected dealing with the case, particularly recovering the remaining money from the Sri Lankan project and dealing with statutory reporting.

Once the outstanding matters have been resolved, FRP expects to dissolve Cleveland Bridge, it said.